Construction Management - Word - c18.rtf

(40 KB) Pobierz

P1: OSO

JWDD004-18 JWDD004-Halpin-v6 August 17, 2005 20:38

Chapter 18

Construction Operations

PROSIDYC: Simulation Program for Construction Operations

The Need

Currently 3D-modelling is the trend in the simulation area. However,

Construction of floating caissons utilized

PROSIDYC as a tool to increase

production.

developing 3D models of construction operations is very complex and time

consuming. In general, the study of construction operations requires a tool

that provides solutions without requiring the input of copious amounts of

data. In order for a construction company to use a simulation tool, the

methodology has to be presented in a very simple and graphical context.

Pictorial and schematic tools are easily accepted. In contrast, if the

methodology appears to be too theoretical or analytical it will be avoided

by construction practitioners.

The Technology

PROSIDYC is a system for simulating construction operations jointly developed by the

Planning and Methods Unit of Dragados y Construcciones, Madrid, Spain and the

Division of Construction Engineering & Management at Purdue University.

PROject SImulation Dragados Y Construcciones (PROSIDYC) is a computer based

system for analyzing construction job site production processes. It is used to improve

productivity in the field by studying resource utilization and cycle times and identifying

opportunities for production improvement. PROSIDYC uses the CYCLic Operations

NEtwork (CYCLONE) modeling format. A set of graphical modeling elements are

utilized to develop a network model of the process of interest. The model identifies

waiting or delay states as well as active productive states. The computer program allows

the modeler to identify resources which are underutilized and bottlenecks in the process.

The use of this approach has achieved 100% success in productivity improvement on

the processes studied. Improvements range from 30% to 200%. Data support the fact that

Harbor site layout.

PROSIDYC/CYCLONE

Flow diagram.

Caisson Construction Valencia, Spain.

18-1

P1: OSO

JWDD004-18 JWDD004-Halpin-v6 August 17, 2005 20:38

18-2 Chapter 18 Construction Operations

for every hour of analyst time used, a saving of $2,000 is realized. Therefore, for 100

hours of engineering-time invested, a saving of $200,000 is achieved. PROSIDYC was

used to achieve major cost savings in the massive breakwater in Valencia shown here.

18.1 MODELING CONSTRUCTION OPERATIONS

In Chapter 1, the hierarchy of construction management was described as shown in Figure

18.1. Activities define the structure of projects. The basic building block required to understand

and analyze construction operations is the work task. A meaningful description

of a construction operation requires the definition of the basic work tasks and the manner

in which the available resources (e.g., cranes, crews, materials, etc.) perform or process

through the work tasks. In this sense individual resources can be said to traverse or flow

through work tasks. The sequential and logical relationships between the various work tasks

define the technology being used. The actual working of the operation can then be described

by locating and monitoring, from time to time, the various resource entities as they dynamically

traverse the static structure of the operation. A simple graphical modeling system

can be used to analyze the work flow and develop the productivity for a given construction

operation.

18.2 BASIC MODELING ELEMENTS

A modeling format for flow modeling construction operations can be developed using four

graphical symbols:

Figure 18.1 Hierarchical levels in construction management.

P1: OSO

JWDD004-18 JWDD004-Halpin-v6 August 17, 2005 20:38

18.3 Building Process Models 18-3

Modeling Element Name of Element

NORMAL

COMBI

QUEUE

ARROW

Description of Modeling Element

The normal work task modeling element can

commence as soon as a unit (e.g. resource)

arrives from a preceding element; it is

unconstrained.

The constrained work task modeling element

requires multiple resources (e.g. cranes,

crews) before it can begin. A combination of

resources is required to start. Otherwise similar

to the normal work task modeling element.

The idle state of a resource entity symbolically

represents a waiting location (i.e. a queue)

where resources wait prior to being combined.

The directional flow modeling element shows

the logical flow of resources.

Figure 18.2 Basic modeling elements.

1. Active-state square node representing a work task

2. Idle-state circle representing a delay or waiting position for a resource entity

3. Directional flowarrowrepresenting the path of a resource entity as it moves between

idle and active states

The symbols used (see Fig. 18.2) for each modeling element are designed to be simple

and helpful in developing schematic representations of the construction operation being

modeled. Two basic shapes (squares and circles) are used to model active and waiting resource

states; together with directed arrows (arcs) for resource flow direction, they help to

provide a quick visual grasp of the structure of a construction operation. These symbols

are the basic modeling elements of the CYCLONE (CYCLic Operations Network) modeling

system. They are used to build networks of active and idle states to represent cyclic

construction processes.

It is convenient to distinguish between the unconstrained (i.e., normal) work task and

the constrained (i.e., requiring the initial satisfaction of conditions) work task. While all

work tasks are modeled schematically as square nodes, the constrainedwork task is modeled

as a square node with a corner slash. Thus a total of four symbols is required for the modeling

of the structure and resource entity flow of construction operations (see Fig. 18.2).

The active working-state models are the NORMAL and COMBI modeling elements.

Both have a square-node format and model work tasks. Since the work task is the basic

component of a construction operation, it should be chosen so that its name or description

is sufficient to convey to a crew member or supervisor the nature, technology, work content,

and resources needed to fulfill the work task.

Simple examples of work task activities are breaking open brick pallets, preparing

column formwork, and loading trucks with front-end loaders. The definition of a work task

thus requires a verbal description, an indication of the resource entities involved, and a

definition of the time required (duration) to complete the task.

18.3 BUILDING PROCESS MODELS

The relative sequence and logic of the work tasks and processes that make up a construction

operation constitute the technological structure of the operation. The modeling elements

can be used in a variety of patterns to model construction operations.

P1: OSO

JWDD004-18 JWDD004-Halpin-v6 August 17, 2005 20:38

18-4 Chapter 18 Construction Operations

Figure 18.3 Schematic outline of earth-moving operation.

As an example, consider the development of a model for an earth-moving operation

that involves the loading of trucks with earth for transport to a dump area. A pictorial

representation of the operation is shown in Figure 18.3; it uses a front-end loader, some

trucks, and earth.

In order to develop the framework of the earth-moving operation, it is necessary to

identify the major resources involved (i.e., trucks, front-end loader, and soil) and establish

the various states (i.e., both the active working states and the passive waiting states) that

the resources traverse in their work assignment paths and cycles. Finally, the integration of

the resource paths and cycles establishes the basic structure of the operation.

Each truck, for example, is idle while it waits (i.e., queues) for loading; it enters active

working states when it is being loaded, dumping, traveling loaded to the work site, and

returning empty for another load. A simple model of this work cycle is shown in Figure

18.4a using a single COMBI ÒLoad truckÓ work task that requires earth and a front-end

loader for initiation; three NORMAL work task elements, ÒLoaded truck travel,Ó ÒTruck

dump activity,Ó and ÒEmpty truck returnÓ; a single QUEUE element, ÒJoin truck queueÓ;

and five arrows indicating the logical relationships between the various truck states.

18.4 STRUCTURE OF CONSTRUCTION OPERATIONS

The front-end loader can be initially modeled by a unit cycle involving the active-state

COMBI element ÒFEL (front-end loader) loading,Ó the idle QUEUE element ÒFEL idle,Ó

and two entity flow directional logic arrows (see Fig. 18.4b).

In Figure 18.4c, a soil path model is shown that uses a source QUEUE node Òsoil

stockpileÓ and a sink destination soil dump QUEUE node together with a COMBI work

task ÒLoaded into truckÓ and NORMAL work tasks ÒTransport by truckÓ and ÒDumpedÓ

to portray the soil involvement in active work states. Finally, four directional arrows are

required to develop the path structure.

The integrated model incorporating the truck and front-end loader cycles together

with the soil path from stockpile to dump is shown in Figure 18.4d. Model integration is

achieved by combining or ÒoverlayingÓ active states which are common to two or more

resource cycles. For instance, Òload truckÓ in the truck cycle is the same active state (work

task) as Òloaded into truckÓ in the soil cycle and ÒFEL LoadingÓ in the loader cycle. These

three states are combined in the integrated model to be one active state ÒLOAD.Ó

P1: OSO

JWDD004-18 JWDD004-Halpin-v6 August 17, 2005 20:38

18.5 Modeling Procedure 18-5

Figure 18.4 Development of operational structure; (a) truck cycle, (b) loader cycle, and

(c) earth-moving operation.

This model can be used as the basis for further development involving dump area

spotters and queues, dozer stockpiling operations, and truck maintenance, as well as the

basis for further detail such as a more precise description of the front-end loader loading

cycle. An extension of the skeletal structure of the earth-moving operation to include dozer

stockpiling and spreading operations together with a dump spotter foreman is shown in

Figure 18.5. A counter element (represented by a flag) has been added to note the point in

the network at which production will be measured.

The foregoing presentation illustrates that the structure of construction operations can

be developed and illustrated through the proper use and labeling of the basic modeling

elements. The model structure can be used in explaining the construction technology and

construction method of the construction operation to field personnel and managers.

18.5 MODELING PROCEDURE

The procedure for modeling a given construction process involves four basic steps. The

steps, as shown in Figure 18.6, are as follows:

1. Flow Unit Identification. As a first step, the modeler must identify the system

resource flow units (e.g., resources such as earth, cranes, crews, etc.) that are

P1: OSO

JWDD004-18 JWDD004-Halpin-v6 August 17, 2005 20:38

18-6 Chapter 18 Construction Operations

Figure 18.5 Model of earth-moving operation.

Figure 18.6 Steps in model formulation.

P1: OSO

JWDD004-18 JWDD004-Halpin-v6 August 17, 2005 20:38

18.7 Concrete Pouring Using a Crane and Bucket 18-7

relevant to system performance and for which transit time information is available

or obtainable from the field. The selection of the flow entities is very important

since it dictates the degree of modeling detail incorporated into the operation model.

2. Development of Flow Unit Cycles. Following identification of the flow units that

appear relevant to the process being modeled, the next step in model formulation

is to identify the full range of possible states that can be associated with each flow

unit and to develop the cycle through which each flow unit passes.

3. Integration of Flow Unit Cycles. The flow unit cycles provide the elemental building

components of the model. The structure and scope of the model are obtained by

the integration of activities that are common to two or more flow unit cycles.

4. Flow Unit Initialization. In order to analyze the model and determine the response

of the system model, the various flow units involved must be initialized, both in

number and initial location. Flow units are initialized at idle or waiting states (i.e.,

Queue Nodes).

Models developed using these basic steps must also be modified to provide for monitoring

of system performance. This leads to a fifth stage of system design in which special

elements for determining system productivity, flow unit characteristics, and other pertinent

information are included in the model structure. These features as well as the use of the

Web-CYCLONE program are described on the web at www.wiley.com\college\halpin.

18.6 TYPICAL REPETITIVE OPERATIONS

The key to modeling operations to determine productivity and balance among resources is

to identify processes that are linear and repetitive. At the production level many processes

are cyclic in nature and can be readily modeled using the CYCLONE modeling format.

In general, processes that are linear or evidence linear characteristics are repetitive and

good candidates to be modeled using a cyclic modeling environment. Some examples of

repetitive or cyclic construction processes are:

1. Concrete pouring

2. Structural steel erection

3. Slurry wall construction

4. Pile Construction (Driven and Augered)

5. Caisson Construction

6. Pipe laying

7. Brick and masonry work

8. Reinforced earth construction

9. Exterior panel installation

10. Window or glass-curtain wall installation

11. Tunneling and tunnel excavation

12. Precast concrete member erection

18.7 CONCRETE POURING USING A CRANE AND BUCKET

Concrete is one of the most commonly used materials in construction. Its versatility and

ease of placement have enabled it to hold its place in the market despite the development

of more sophisticated materials. Concrete may be used in many different ways on a project

to include monolithic foundation pours and precast panels to form the building exterior.

P1: OSO

JWDD004-18 JWDD004-Halpin-v6 August 17, 2005 20:38

18-8 Chapter 18 Construction Operations

Concrete can be either cast in place on-site or precast off-site and transported to the project

for installation. The methods of placement at the site vary and depend on a number of

considerations such as (1) the placement location, (2) the desired speed of placement, and

(3) the types of equipment available. In this section, a simple model for the placement of

cast in place concrete using a crane-bucket system will be discussed.

It is assumed that forms and steel reinforcement are in place and that the system is not

constrained by the batch plant (i.e., the quantity of concrete available is not a constraint).

Required resources for the model include concrete hauling trucks, a crane with bucket(s),

vibrating and finishing apparatus, and a crew of laborers at the placement site.

To provide a context for this model, assume that the concrete is to be placed on

a paving job and that the concrete is batched at a site 2 miles from the paving site.

Rather than arriving at the site as a wet mix, five-at-a-time dry batches are carried in

an open-bay truck (with appropriate compartments) to a mixer near the paving site. The

batches are then dumped individually and sequentially into the skip of the mixer and

mixed sequentially, starting with batch 1 and ending with batch 5. As each wet batch

exits the mixer, it is dumped into a concrete bucket and lifted by a crane to the placement

location where it is dumped, spread, vibrated, and finished by a concrete crew.

A schematic diagram of the process is shown in Figure 18.7a. Although dry-batching

operations of this type are not common, this situation provides a good opportunity to

utilize various modeling features. A crane and bucket placement operation is shown in

Figure 18.7b.

A CYCLONE model of the process is shown in Figure 18.8. The model consists of six

cycles representing the various flow units involved. The units and cycles of interest are:

1. Batch plant

2. Trucks

3. Mixer

4. Crane

5. Bucket

6. Laborer crew for spreading, vibrating, and finishing

The process begins with trucks being loaded at the batch tower (COMBI 2). The trucks

consist of five compartments, which are defined by baffles or dividers that are pinned in such

a way that they can be released individually (one at a time) when the truck bed is elevated.

Dry batches are loaded into each of the five compartments. This requires five individual

loads at COMBI 2. The demand for five loads is generated using the GENERATE function

at QUEUE node 9. The GENERATE function takes a single truck unit arriving at 9 and

splits it into 5 units to be processed (i.e., compartments to be loaded).

When five batches are loaded, the CONSOLIDATE at FUNCTION node 3 assembles

the five loads into a single truck for travel to the mixer. Upon arriving at the mixer, the truck

is again reconfigured to represent the five dry batches using the GENERATE function at

QUEUE node 5. Each of the five dry batches are dumped sequentially into the skip of the

mixer.

The mixer processes the batches in sequence and converts them into wet batches for

transport to the placement site. The space in the mixer is represented by a flow unit at

QUEUE node 13. If one unit is initialized at QUEUE node 13, this means that the mixer is

a single-drum unit and only one batch at a time can be processed. If two units are defined

at QUEUE node 13, then the mixer is a dual-drum unit and two batches can be processed

simultaneously (in tandem).

Once a batch is dumped into the skip of the mixer, it is moved to the drum, where water

is added and it is mixed (NORMAL 10). Following mixing, it occupies space in the drum

P1: OSO

JWDD004-18 JWDD004-Halpin-v6 August 17, 2005 20:38

18.7 Concrete Pouring Using a Crane and Bucket 18-9

Figure 18.7 (a) Dry-batch delivery and placement and (b) crane-bucket concrete placement.

P1: OSO

JWDD004-18 JWDD004-Halpin-v6 August 17, 2005 20:38

18-10 Chapter 18 Construction Operations

Figure 18.8 Dry-batch and delivery placement model.

(QUEUE node 11) until it can be dumped to the concrete bucket. Therefore, the space in

the drum is not free until the bucket is filled at COMBI 12, and this is represented by the

feedback loop to QUEUE node 13 (the space QUEUE). That is, space becomes available

after the bucket is filled. This availability of space is required before the next dry batch can

be loaded into the mixer at COMBI 6.

Once all five batches on the truck have been loaded to the mixer at COMBI 6 is free to

return to the batch plant. The fact that the truck is empty (five batches loaded into the mixer)

is established by the CONSOLIDATE at FUNCTION node 7. The empty compartments are

reassembled into a single empty truck that returns to the batching power.

When the bucket is filled, it is available to be lifted by the crane to the placement

location in the pavement. If only one bucket is used, the crane and bucket can be considered

a single unit, and the separate QUEUE node 17 for ÒCrane readyÓ is redundant.

However, if two buckets are used, the crane is a separate unit. After swinging back, it

drops one bucket and picks up the other. This is more efficient since the bucket at the

mixer can be filled while the crane is swinging and placing the other. The second bucket

provides a storage point and keeps the crane active, allowing it to pick up the next loaded

bucket without having to wait during the ÒFill bucketÓ activity at 12. For this reason,

...

Zgłoś jeśli naruszono regulamin