Construction Management - pdf - c09.pdf
(
665 KB
)
Pobierz
P1: OSO
JWDD004-09
JWDD004-Halpin-v6
July 27, 2005
12:58
Chapter
9
Project Cash Flow
Scenario Testing
The Need
Construction company operations are project based. Cash flows can be
estimated by attempting to assess flows from (1) projects in progress,
(2) projects under contract but not yet begun, and (3) potential projects
which will start during the coming financial accounting period. These
sources of income can be viewed as (1) Birds in the hand, (2) Birds in
the bush, and (3) Birds flying in the sky. In other words, cash flows can
be projected from projects in progress and projects which may, with
some probability, start in the coming period for which forecasts are
being made. The advent of spreadsheet analysis and high speed com-
puting has led to “scenario testing” of future cash flow expectations.
Cash Flow Diagram
The Technology
Spreadsheets allow managers to run probabilistic cash flow projections that take into
account the factors noted above. More advanced analysis can also factor in historical
evidence of payment trends and the potential impact of macroeconomic factors. These
techniques go beyond the typical best-, expected-, and worst-case scenario modeling and
may rely on Monte Carlo simulation, Markov modeling, or the use of “fuzzy” data sets to
build up statistically valid outcomes. At the most advanced level, when future cash flows
are tied to a multitude of unknowns, probabilistic techniques may be employed in
combination with real-options theory to gain an improved view of the impact of a
financial decision (e.g., accepting or declining a project or changing market strategy) on
value creation for a company. This level of analysis used to be in the economist’s realm,
butisnow commonplace in the finance and business development groups of corporations.
9.1
CASH FLOW PROJECTION
The projection of income and expense during the life of a project can be developed from sev-
eral time-scheduling aids used by the contractor. The sophistication of the method adopted
usually depends on the complexity of the project. In many contracts (e.g., public contracts
such as those used by state agencies), the owner requires the contractor to provide an S-curve
of estimated progress and costs across the life of the project. The contractor develops this
by constructing a simple bar chart of the project, assigning costs to the bars, and smoothly
connecting the projected amounts of expenditures over time.
Consider the highly simplified project (Fig. 9.1) in which four major activities are
scheduled across a four-month time span. Bars representing the activities are positioned
along a time scale indicating start and finish times. The direct costs associated with each
activity are shown above each bar. It is assumed that the monthly cost of indirect charges
(i.e., site office costs, telephone, heat, light, and supervisory salaries, which cannot be
147
P1: OSO
JWDD004-09
JWDD004-Halpin-v6
July 27, 2005
12:58
148
Chapter 9
Project Cash Flow
Figure 9.1
Development of the S-curve.
charged directly to an activity) is $5,000. Assuming for simplicity that the direct costs are
evenly distributed across the duration of the activity, the monthly direct costs can be readily
calculated and are shown below the time line. The direct charges in the second month,
for example, derive from activities A, B, and C, all of which have a portion in the period.
The direct charge is simply calculated based on the portion of the activity scheduled in the
second month as:
Activity
A
:
1
2
×
50
,
000
=
$25
,
000
Activity
B
:
1
2
×
40
,
000
=
$20
,
000
Activity
C
:
1
3
×
60
,
000
=
$20
,
000
$65
,
000
The figure shows the total monthly and cumulative monthly expenditures across the life of
the project. The S-curve is nothing more than a graphical presentation of the cumulative
expenditures over time. A curve is plotted below the time-scaled bars through the points of
cumulative expenditure. As activities come on-line, the level of expenditures increases and
the curve has a steeper middle section. Toward the end of a project, activities are winding
down and expenditures flatten again. The points are connected by a smooth curve since the
assumption is that the expenditures are relatively evenly distributed over each time period.
This curve is essentially a graphical portrayal of the outflow of monies (i.e., expense flow)
for both direct and indirect costs.
9.2
CASH FLOW TO THE CONTRACTOR
The flow of money from the owner to the contractor is in the form of progress payments.
As already noted, estimates of work completed are made by the contractor periodically
P1: OSO
JWDD004-09
JWDD004-Halpin-v6
July 27, 2005
12:58
149
9.2
Cash Flow to the Contractor
Figure 9.2
Expenses and income profiles.
(usually monthly) and are verified by the owner’s representative. Depending on the type
of contract (e.g., lump sum, unit price, etc.), the estimates are based on evaluations of the
percentage of total contract completion or actual field measurements of quantities placed.
This process is best demonstrated by further consideration of the four-activity example just
described. Assume that the, contractor originally included a profit or markup in his bid of
$50,000 (i.e., 25%) so that the total bid price was $250,000. The owner retains 10% of all
validated progress payment claims until one-half of the contract value (i.e., $125,000) has
been built and approved as an incentive for the contractor to complete the contract. The
retainage will be deducted from the progress payments on the first $125,000 and eventually
paid to the contractor on satisfactory completion of the contract. The progress payments will
be billed at the end of the month, and the owner will transfer the billed amount minus any
retainage to the contractor’s account 30 days later. The amount of each progress payment
can be calculated as:
Pay
=
1.25(indirect expense
+
direct expense)
−
0.10[1.25(indirect expense
+
direct expense)]
The minus term for retainage drops out of the equation when 50% of the contract has been
completed. Because of the delay in payment of billings by the owner and the retainage
withheld, the revenue profile lags behind the expense S-curve as shown in Figure 9.2.
The revenue profile has a stair-step appearance since the progress payments are trans-
ferred in discrete amounts based on the preceding equation. The shaded area in Figure 9.2
between the revenue and expense profiles indicates the need on the part of the contractor
to finance part of the construction until such time as he is reimbursed by the owner. This
difference between revenue and expense makes it necessary for the contractor to obtain
temporary financing. Usually, a bank extends a line of credit against which the contrac-
tor can draw to buy materials, make payments, and pay other expenses while waiting for
reimbursement. This is similar to the procedure used by major credit card companies in
which they allow credit card holders to charge expenses and carry an outstanding balance
for payment. Interest is charged by the bank (or credit card company) on the amount of
the outstanding balance or overdraft
1
.Itis, of course, good policy to try to minimize the
amount of the overdraft and, therefore, the interest payments. The amount of the overdraft is
1
Similar examples of this type of inventory financing can be found in many cyclic commercial undertakings.
Automobile dealers, for instance, typically borrow money to finance the purchase of inventories of new car
models and then repay the lender as cars are sold. Clothing stores buy large inventories of spring or fall fashions
with borrowed money and then repay the lender as sales are made.
P1: OSO
JWDD004-09
JWDD004-Halpin-v6
July 27, 2005
12:58
150
Chapter 9
Project Cash Flow
Figure 9.3
Influence of front, or mobilization, payment on expense and income profiles.
influenced by a number of factors, including the amount of markup or profit the contractor
has in his bid, the amount of retainage withheld by the owner, and the delay between billing
and payment by the owner.
Interest on this type of financing is usually quoted in relationship to the prime rate.
The
prime rate
is the interest rate charged preferred customers who are rated as very
reliable and who represent an extremely small risk of default (e.g., General Motors,
Exxon, etc.). The amount of interest is quoted in the number of points (i.e., the num-
ber of percentage points) above the prime rate. The higher-risk customers must pay more
points than more risky borrowers. Construction contractors are normally considered high-
risk borrowers; if they default, the loan is secured only by some materials inventories
and partially completed construction. In the event that a manufacturer of household ap-
pliances defaults, the inventory of appliances is available to cover part of the loss to
the lender. Additionally, since construction contractors have a historically high rate of
bankruptcy, they are more liable to be charged higher interest rates in most of their financial
borrowings.
Some contractors offset the overdraft borrowing requirement by requesting front, or
mobilization, money from the owner. This shifts the position of the revenue profile so that
a reduced, or zero, overdraft occurs (Fig. 9.3). Since the owner is normally considered less
of a risk than the contractor, he can borrow short-term money at a lower interest rate. If
the owner agrees to this approach, he essentially takes on the interim financing requirement
normally carried by the contractor. This can occur on cost-reimbursable contracts where
the owner has great confidence in the contractor’s ability to complete the project. In such
cases it represents an overall cost savings to the owner, since otherwise he will ultimately
be back-billed for the contractor’s higher financing rate if the contractor must carry the
overdraft.
9.3
OVERDRAFT REQUIREMENTS
In order to know how much credit must be made available at the bank, the contractor needs to
know what the maximum overdraft will be during the life of the project. With the information
given regarding the four-activity project, the overdraft profile can be calculated and plotted.
For purposes of illustration, the interest rate applied to the overdraft will be assumed to
be one percent per month. That is, the contractor must pay the bank 1% per month for the
amount of the overdraft at the end of the month. More commonly, daily interest factors may
be employed for the purpose of calculating this interest service charge. Month-end balances
might otherwise be manipulated by profitable short-term borrowings at the end of the
month. The calculations required to define the overdraft profile are summarized in Table 9.1.
Table 9.1
Overdraft Calculations
Month
1
2
3
4
5
6
Direct cost
$25,000
$65,000
$75,000
$15,000
Indirect cost
5,000
5,000
5,000
5,000
Subtotal
30,000
70,000
80,000
20,000
Markup (25%)
7,500
17,500
20,000
5,000
Total billed
37,500
87,500
100,000
25,000
Retainage withheld
(10%)
3,750
8,750
0
0
Payment received
$33,750
$78,750
$100,000
$37,500
Total cost to date
30,000
100,000
180,000
200,000
200,000
Total amount billed
to date
37,500
125,000
225,000
250,000
250,000
Total paid to date
$33,750
112,000
212,500
250,000
Overdraft end of
month
30,000
100,300
147,553
90,279
(8,818)
b
(46,318)
b
Interest on overdraft
balance
a
300
1,003
1,476
903
0
0
Total amount
30,300
101,303
149,029
91,182
(8,818)
financed
a
A simple illustration only. Most lenders would calculate interest charges more precisely on the amount/time involved employing daily interest factors.
b
Parentheses indicate a positive balance in this case.
Plik z chomika:
Januszek66
Inne pliki z tego folderu:
Back Seat_ A Mumbai Tale - Aditya Kripalani.mobi
(755 KB)
Brief Wondrous Life of Oscar Wao, The - Junot Diaz.opf
(3 KB)
Don't Make Me Think, Revisited_ - Steve Krug.mobi
(9256 KB)
M. T. Anderson - Norumbegan 03 - The Empire of Gut and Bone # (v5.0).epub
(2209 KB)
M. T. Anderson - Norumbegan 02 - The Suburb Beyond the Stars # (v5.0).epub
(2105 KB)
Inne foldery tego chomika:
Dokumenty
Galeria
LUDLUM ROBERT
Midi - Kar
Mszał Rzymski PL
Zgłoś jeśli
naruszono regulamin